|  
  
  
   
  
  
  
     |   
 A first principles assessment
 Why introduce urban road charging?
 Demand impacts
 Short and long run demand responses
 Level of response
 Supply impacts
 Financing requirements
 Expected impact on key policy objectives
 Contribution to objectives
 Expected impact on problems
 Expected winners and losers
 Barriers to implementation
 Why introduce urban road charging?  The 
        underlying argument for urban road charging is that road users should 
        be directly charged for the additional costs which their use of road space 
        imposes on the rest of society. Economists argue that charges for goods 
        and services should reflect the costs imposed on society by the users 
        of those goods or services. Whilst the users of urban road space themselves 
        bear some of the costs which they impose (delay to their journey, increased 
        risk of themselves being involved in an accident, exposure of themselves 
        to local air pollution), the additional costs to the rest of society which 
        their use of road space imposes (delay to other road users, the increased 
        risk of other road users being involved in an accident, exposure of others 
        to local air pollution etc) are not fully charged for.
 The current failure, in many towns and cities, to fully charge for these 
        additional costs means that charges are currently too low. It is generally 
        recognized that the charge levied for a good or service will influence 
        the quantity of that good or service that people demand. Hence, if charges 
        are too low then demand will be too high, resulting in congestion, environmental 
        degradation and increased risk of accidents. Urban road charging, therefore, 
        seeks to correct for this and, hence, to re-allocate road space according 
        to road users' willingness to pay. In doing so, this will lead to a reduction 
        in traffic and will generate revenue which can then be invested in useful 
        projects.  Demand impacts The impacts of urban road charging are, almost exclusively, on the demand 
        for road travel, usually travel by car. This determines the way in which 
        it contributes to transport policy objectives.  Urban road charging could impact on people's demand in a number of different 
        ways and the precise way in which it will do so will differ according 
        to the situation. Responses and situations summarises how people's responses 
        may be affected in different situations.  
 
   
    |  | = 
      Weakest possible response, |  | = 
      strongest possible positive response |   
    |  | = Weakest 
      possible negative response, |  | = strongest 
      possible negative response |  
  
    |  | = No response |  Short and long run demand responses Demand responses to urban road charging in the short run are likely to 
        be different to those which might take place in the longer run. This is 
        because certain decisions which have major impacts on people's travel 
        behaviour, such as where to live and whether or not to own a car, are 
        not generally subject to review in the short run. Demand responses illustrates 
        the different types of response to urban road charging which might be 
        expected to occur in the short, medium and longer term. 
 
   
    |  | = 
      Weakest possible response, |  | = 
      strongest possible positive response |   
    |  | = Weakest 
      possible negative response, |  | = strongest 
      possible negative response |  
  
    |  | = No response |   
        
 Level of response
 Price elasticity of demand will also vary according to context. 
          Important factors influencing the calculation and interpretation of 
          price elasticities include: the size of the price change; the type of 
          pricing mechanism; the type of trip; the type of traveler; the price 
          of related goods and services; and whether the elasticity accounts for 
          short term or more long term demand responses. Hence, care should be 
          taken, if applying price elasticities, that they are based on a similar 
          context to that in which they are being applied.
 Whilst there are few estimates of the generalized cost elasticity of 
        demand for car travel, a recent study (Lee, 2000) reports estimates of 
        short run generalized cost elasticity in the range -0.5 to -1.0 and estimates 
        of long run generalized cost elasticity in the range -1.0 to -2.0. Before 
        applying these generalized cost elasticities to urban road charging one 
        would need to calculate by what percentage the introduction of urban road 
        charging would alter the generalized costs of car travel. A relatively 
        moderate charge might increase generalized costs by approximately 10% 
        which, it is suggested, would decrease car travel by at least 5% in the 
        short run and by at most 20% in the long run. Supply impacts
 Urban road charging would not usually involve any change in overall road 
        supply, except where road closures or other traffic management measures 
        have to be implemented in order to make a cordon system work. However, 
        because demand is reduced, the amount of road space available to each 
        individual vehicle is increased. Furthermore, in order to cope with expected 
        increases in demand for public transport it may be necessary to increase 
        public transport supply in advance of the charge being implemented.
 Financing requirements
 Certain forms of urban road charging are cheaper to implement than others. 
        This depends principally on the complexity of the system, the technology 
        chosen and the system of enforcement.
 The following cost and revenue estimates were calculated for two studies 
        of the feasibility of urban road charging in London, based on a simple 
        central London scheme: 
         
          |   | Licence | Tag | Smart Card |   
          | Implementation costs | £30-50M 
 | £85M | £140M |   
          | Annual operating costs | £30M - £50M 
 | £55M | £55M |   
          | Revenues | £150M -£570Mpa | £150M - £570Mpa | £150M - £570Mpa |  Annual operating costs for the London scheme have turned out to be significantly 
        higher than shown in the table above and currently stand at about £90 
        million per annum. Extra buses required cost a further £5 million 
        per annum. 
 
 Expected impact on key policy objectives  Urban road charging encourages people to change their car travel behaviour. 
        It firstly encourages them to change the timing and location of their 
        car journeys from congested and environmentally sensitive times and places, 
        e.g. peak hours in city centres, to less congested, less sensitive times 
        and places. Secondly, it encourages them to reduce their overall level 
        of car-use, either by switching from car to other transport modes or by 
        reducing the amount they travel. Therefore, its main contributions will 
        be to objectives concerned with efficiency and environment. It will also 
        generate substantial revenue, which can potentially be used to finance 
        other elements of a transport strategy (May et al, 1992). Contribution 
        to objectives assesses its scale of contribution to the 6 key objectives. 
        Contribution to objectives 
         
          | Objective  | Scale of contribution 
           | Comment  |   
          | 
 | 
 | By reducing delays, improving 
              reliability and prioritising high value trips  |   
          | 
 | 
 | By improving streetscape 
              and urban design and by reducing community severence  |   
          | 
 | 
 | By reducing air and noise 
              pollution and pressures on green space and environmentally sensitive 
              sites  |   
          | 
 |  *
 | By improving public transport 
              conditions and releasing revenue which can be used for the ‘common 
              good’  |   
          | 
 | 
 | By reducing traffic levels 
              and evening out traffic speeds  |   
          | 
 | 
 | By freeing up potentially 
              productive time currently lost in congestion and by enabling freight 
              operators to rationalize their fleet operations  |   
          | 
 | 
 | By raising substantial amounts 
              of revenue on an on-going basis  |  
 
   
    |  | = Weakest 
      possible positive contribution, |  | = strongest 
      possible positive contribution |   
    |  | = Weakest 
      possible negative contribution |  | = strongest 
      possible negative contribution |  
   
    |  | = 
      No contribution |  
  *Is somewhat dependent on how the revenue raised is spent.
 Expected impact on problems Urban road charging could significantly reduce car use in the charged 
        area, and hence reduce delays, unreliability, environmental impact and 
        accidents. Traffic would divert to boundary routes, other times of day 
        and other modes; much of the transfer would be to bus, which would benefit 
        from the reduced congestion. Careful design is needed to ensure that these 
        alternatives do not themselves become congested, and for cordon schemes, 
        the location of the controls is critical. Subject to this, congestion 
        charging can achieve significant road user travel time, environmental 
        and safety benefits. It will also generate substantial revenue, which 
        can potentially be used to finance other elements of a transport strategy 
        (May et al, 1992). Contribution to alleviation of key problems assesses 
        the scale of contribution to the alleviation of the 14 key problems.   
        
           
            | Contribution to alleviation of key problems |  
         
          | Problem   | Scale of contribution 
           | Comment  |   
          | Congestion-related delay 
           | 
 | By reducing traffic volumes 
              though re-routing and re-scheduling may transfer problems elsewhere 
           |   
          | Congestion-related unreliability 
           | 
 | By reducing traffic volumes 
              though re-routing and re-scheduling may transfer problems elsewhere 
           |   
          | Community severence  | 
 | By reducing traffic volumes 
              and enabling some roads to be closed  |   
          | Visual intrusion  | 
 | By reducing traffic volumes 
              and land-take  |   
          | Lack of amenity  | 
 | By discouraging longer journeys 
              and enhancing the viability of local facilities  |   
          | Global warming  | 
 | By reducing traffic-related 
              CO2 emissions  |   
          | Local air pollution  | 
 | By reducing emissions of 
              NOx, particulates and other local pollutants though re-routing 
              and re-scheduling may transfer problems elsewhere  |   
          | Noise  | 
 | By reducing traffic volumes 
              though re-routing and re-scheduling may transfer problems elsewhere 
           |   
          | Reduction of green space 
           | 
 | By reducing pressure for 
              new road building and city expansion  |   
          | Damage to environmentally 
              sensitive sites  | 
 | By reducing traffic volumes 
           |   
          | Poor accessibility for those 
              without a car and those with mobility impairments  | 
 | By enhancing the viability 
              of public transport and by discouraging car-oriented development 
           |   
          | Disproportionate disadvantaging 
              of particular social or geographic groups  | 
 | By enhancing the viability 
              of public transport and reducing traffic levels in residential areas, 
              though people living on the boundary of the charged area may also 
              experience disbenefits *  |   
          | Number, severity and risk 
              of accidents  | 
 | By reducing traffic volumes 
           |   
          | Suppression of the potential 
              for economic activity in the area  | 
 | By freeing-up time previously 
              spent in congestion and by improving the efficiency of the local 
              road network  |  
 
   
    |  | = Weakest 
      possible positive contribution, |  | = strongest 
      possible positive contribution |   
    |  | = Weakest 
      possible negative contribution |  | = strongest 
      possible negative contribution |  
   
    |  | = 
      No contribution |  
 
 
 Expected winners and losers We would not necessarily expect everyone to directly benefit from the 
        introduction of urban road charging. Winners and losers highlights the 
        main groups of people who we would expect to be direct beneficiaries, 
        as well as those who we would expect, in the first instance at least, 
        to lose out. It should be remembered, however, that this only relates 
        to the direct, immediate impacts and that the revenue generated from urban 
        road charging would, depending on how it is used, enable everyone to benefit. 
        For example, it would be possible to use some of the charging revenue 
        to reduce general business taxes on small businesses or to reduce income 
        tax for people on low incomes. 
         
          | Group  | Winners/Loses  | Comment  |   
          | Large scale freight and commercial 
              traffic  | 
 | High value journeys – 
              less time spent in congestion the greater the vehicle utilization 
              – relatively small proportion of journey distance in urban 
              conditions.  |   
          | Small businesses  | ? | Some small, local businesses 
              will find themselves spending a high proportion of their time in 
              the charged area, potentially resulting in a large proportionate 
              increase in their transport costs, though they are likely to benefit 
              from reduced congestion.  |   
          | High income car-users  | 
 | High income associated with 
              high value of time and, hence, highly valued time savings from reductions 
              in congestion, and charge is likely to be a relatively small proportion 
              of disposable income.  |   
          | Low income car-users with 
              poor access to public transport  | ? | Low income car-users may 
              be inconvenienced by being deterred from making particular car journeys, 
              although they may find that improved public transport makes it an 
              attractive alternative. Overall impact will depend significantly 
              on how revenues are used.  |   
          | All existing public transport 
              users  | 
 | These people will face an 
              increase in their transport costs but will find it difficult, in 
              the short run at least, to change their travel arrangements and 
              behaviour. However, increased demand for alternatives may result 
              in their increased availability.  |   
          | People living adjacent to 
              the area targeted  | ? | Reduced congestion will result 
              in enhanced reliability and reduced journey times for public transport, 
              whilst increased demand for alternatives should result in increased 
              supply; a possibility of increased over-crowding but overall impact 
              dependent on how road pricing revenues are used. Traffic levels 
              in the area where they live may increase or decrease depending on 
              the location. |   
          | People making high value, 
              important journeys  | 
 | If using car then they are 
              likely to benefit from improved speed and reliability (although 
              at some extra financial cost). If using public transport, then in 
              the longer term at least, the quality of service should have improved. |   
          | The average car user |  | Average car-users with middle incomes will 
            tend to either be encouraged to change mode (or making some other 
            alternative arrangements) or will pay the charge which, because of 
            their value of time, may not represent good value to them i.e. the 
            decongestion benefits will not compensate them for the charge. Overall 
            impact dependent on how road pricing revenues are used. |  
 
   
    |  | = 
      weakest possible benefit, |  | = 
      strongest benefit |   
    |  | = weakest 
      possible disbenefet, |  | = strongest 
      possible disbenefit |  
   
    |  | = neither 
      wins nor loses |  
 
 Barriers to implementationCertain forms of urban road charging are more easily implementable than 
        others. The complexity of the system and the technology chosen are important 
        factors determining ease of implementation. However, further, perhaps 
        even more important, factors will be the way in which the policy is presented 
        to the public, the public acceptability of the policy and whether the 
        necessary legal powers are in place.
 
         
          | Barrier | Scale | Comment |   
          | Legal |  | In some countries legislation 
            may need to be passed in order to enable road pricing |   
          | Finance |  | Planning and preparing for implementation 
            may involve considerable human resources and some investment in technology, 
            but a large element of these may be offset against the substantial 
            expected revenues once the system is implemented |   
          | Political |  | Public and, hence, political 
            opposition is generally quite widespread and vocal |   
          | Feasibility |  | Very much dependent on the complexity 
            of the system adopted, though all types of system will require considerable 
            planning and on-going management |  
 
  * 
      Is dependent on which form of charging scheme is to be implemented 
    |  | = 
      minimal barrier, |  | = 
      most significant barrier |  
 
  
 
 
 
 |