                    WORKPLAN
                   The 
                    workplan consists of a Methodological 
                    Phase (months 0-6), an Experimental 
                    Phase (months 9-24) and a Validation 
                    Phase (months 25-34). Seven WorkPackages have been 
                    developed. The function of each is distinct, but provides 
                    outputs relevant to other WPs.  One workpackage is dedicated 
                    to project management and another to dissemination and consultation 
                    activities.  
                     
                    The workplan is structured into workpackages.  Each of the 
                    research workpackages (WP1, 2, 3 and 4) approach separate 
                    parts of the research question. The results of each of these 
                    workpackages have implications for the direction of the subsequent 
                    ones. The project is scheduled for 36 months with a “long, 
                    thin” workpackage (WP0) devoted to management functions (including 
                    administration and financial procedures) (see Figure 
                    1).  
                     
                     
                     
                     
                     
                    Figure 1.  Interaction between workpackages 
                     
                     
                      
                     
                     
                     
                     
                      
                   
                    
                   
                   
                   
                   
                   
                   
                 | 
               
             
           |