OVERVIEW OF MILESTONES

Milstone No.
Month Due
Output WP
Milestone Objectives
Decision Criteria for Assessment

M1

6
WP1
Completion of tasks 1.1-1.4 and integration for Deliverable 1. Full collation and appraisal of the methods and metrics to be used in the experimental studies; practicality of proposed approaches within the project resources; consistency of approaches between proposed methods.
M2
9
WP2
Formalisation of experimental methodology (completion of task 2.1) Formal understanding between partners of the experimental design, measures to be used and analysis to be undertaken.
M3
21
WP2
Completion of data collection for interpretation Data collection completed.
M4
24
WP3
Interpretation of experimental findings for risk analysis and validation WP3 leader is able to interpret the findings from WP2 in order to provide a draft specification of the HASTE test regime. WP4 leader receives findings for inclusion in risk analysis.
M5
26
WP3
Develop a set of specification for conducting IVIS safety evaluations (task 3.1) Formal understanding by partners of the validation methodology. Agreement on the real systems to be evaluated.
M6
32
WP3
Collation of validation exercise Partners provide WP3 leader with validation study results. Collation and comparison across methodologies.
M7
33
WP4
Completion of risk analysis and diagnostics Formalisation of methodology for the hazard identification and risk analysis
M8
26
WP5
Prepare draft specification for HASTE test regime IHRA-ITS, ACEA and Eucar workshops to discuss draft specification for HASTE test regime
M9
34
WP5
Workshop in Brussels Dissemination of project outputs
M10
36
WP6
Completion of final report Methodologies and protocol are critically appraised. Suggested HASTE protocol is defined.